SH-152 has carried two-way traffic between Mustang and Union City since at least early July. The City of Mustang's July 2, 2026 City Manager's Report said ODOT's reconstruction of that stretch was complete. For drivers who spent spring on ODOT detours west of Richland Road, that was the change that mattered.
The new pavement was only the first stage. The traffic signals at every SH-152 intersection in Mustang are next. One of the corridor's best-known restaurant buildings is being divided among three new tenants. The roads, sidewalks and trails that feed into the highway get their turn after that, with work scheduled into 2027. A drive down 152 next spring will feel different from one today for reasons that have nothing to do with the asphalt.
Early in the year, SH-152 was a patchwork. The city's May 29 report said two-way traffic was open between Clear Springs and Richland roads, westbound through traffic west of Richland still had to use ODOT detours, and ODOT expected substantial completion in June. By the July 2 report, the reconstruction was complete and the full stretch to Union City was open both ways.
ODOT's records are a step behind. Its August 2026 monthly construction report still listed the 9.88-mile SH-152 "grade, drain, and surface" contract as under construction, with 98.54% of the contract amount paid. The two records don't contradict each other. The lanes are open, and the contract hadn't been formally closed out as of late summer. Some of the information on the city's general projects page is older still: it describes a westbound closure with work expected through fall 2025. The July report has replaced that.
Once the pavement was finished, the city turned to the intersections. On March 30, 2026, Mustang announced a $560,000 grant from the Association of Central Oklahoma Governments' Air Quality Grant Program for SH-152 signal work. According to the October 2 City Manager's Report, the grant covers 80% of the project's cost, which puts the total at about $700,000. It pays to replace the controllers, conflict-monitoring equipment and vehicle-detection equipment at all of the intersections along SH-152 in Mustang.
The city has put a target on it. Once the system is finished, staff expect congestion delay along SH-152 in Mustang to drop by 20% to 30%. It is designed to improve communication and coordination between the corridor's signals. That figure is a projection made before installation. As of October 2, staff were still choosing the new signal system, and equipment replacement was expected to begin "later this Fall." For drivers, the reconstruction already changed the road surface. The signal work will change how long they sit at each light.
The signal upgrade arrives as the businesses along the corridor are changing. The clearest example is the former Applebee's at 1020 E. SH-152, which Central Oklahoma Weeklies reported closed effective April 28, 2025. The building is being split into tenant spaces. The city's October 2 report lists finish-out permits for three of them:
None of the three has announced an opening date. The building held one sit-down restaurant for years. When it reopens, it will hold a drive-thru coffee stop and two quick-service kitchens on the same stretch of highway that is getting new signal timing.
The former Applebee's is the largest change, but several smaller projects have already been completed on or just off the corridor this year:
Another commercial project is not open yet. Ashton Gray holds a permit for an 8,023-square-foot retail center at 215 N. Sara Road. As of October 2, the interior work and the sewer line still had to be completed, and no tenants had been named.
Several more SH-152 addresses have appeared in the city's license filings this year. These are applications, not openings. Relentless Performance at 536 W. SH-152 and Family Freight Academy at 2107 E. SH-152 applied for business licenses in the May 29 report. Basecamp Journey Academy at 1720 E. SH-152, Gen X Garage Door Pros at 520 W. SH-152 and H&R Block at 1106 E. SH-152 followed in the July 2 report.
With the highway itself finished, the work is moving to the streets that connect to it. The first is Clear Springs Road between SW 89th Street and SH-152. The city had planned to resurface it during fall break, starting October 14, after a delay caused by limited crews and equipment. A city notice dated October 15 moved the start to Friday, October 16. That notice called for through traffic to be closed with local access kept open, flaggers running one lane of traffic and crews working on Saturday. The city expected to finish the following week, weather permitting.
After that, the larger projects begin in 2027. Two of them are small in size but would change how people get to the highway on foot:
The Mustang Trails project ends at the highway, and that ties these projects together. The rebuilt pavement and the new signal system serve drivers. The trail will give people walking from Wild Horse Park a route that ends on SH-152 beside Fire Station #1. Redlands Contracting's 2027 start dates are the next ones to watch on the city's monthly reports.
If you own a home or commercial property near the SH-152 corridor and want to know how this year's openings and next year's construction schedule could affect it, Access Real Estate follows the city's reports month to month and can walk you through what's changing near your address. Work With Us.
Stay up to date on the latest real estate trends.
Give us a call when you are ready to make a move. We would be honored to assist with any and all of your Oklahoma Real Estate needs.